The Mountain Valley Pipeline project, a 303-mile methane gas pipeline is facing another delay and an increase in costs. This delay is now pushing the project’s completion to the first quarter of 2024 which is still not confirmed. However, the factor behind this delay is still unforeseen. The project initially started in 2014 with an overall estimated budget of $3.5 billion and was expected to be completed by 2018.
The Project’s Turbulent Journey
According to the reports, the project has seen a series of unexpected events that cause delays and other issues to the project. Besides that, the project was originally estimated at $3.5 billion with a target completion by the end of 2018, but it is still in the development phase with further delays. The Mountain Valley Pipeline project has unfortunately encountered a lot of hurdles and setbacks over the years and contractors are now in deep grief regarding its completion. It’s jointly owned by Equitrans Midstream, NextEra Energy, Consolidated Edison, AltaGas, and RGC Resources.
Continual Cost Increases
when a giant developmental project gets unexpected delays, it ultimately hikes up the cost of the project. this is due to certain factors including the fluctuation of market prices for fuel, material and labor costs in general.
Since the project was about to be completed in 2018, the completion cost of the project ($3.5 billion) was according to the market hike of that time. However, the project’s latest cost projection stands at $7.2 billion which is a really big rise from the initial $3.5 billion estimate. Some unforeseen variables play quite a bit of a role in these cost escalations, accounting for more than half of the increase, according to Equitrans Midstream Corp.’s report to the Securities and Exchange Commission (SEC).
The Factors that are Contributing to Delays and Costs
The continuous delay in this giant pipeline project is not clear and under the hidden rubbles. However, contractors and experts are trying to intelligently guess the matter to overcome the issue and make a better foolproof plan. According to the experts, some of the possible reasons behind the project delay are:
A Complex Terrain and Geology
It is a simple and most accepted guess that due to the location of the project; the competition is in the drain. As the steel pipeline project lies in the Jefferson National Forest which is crossing the mountain valley, it is causing trouble for the contracts and even for the equipment to work on it.
The challenging terrain and geology of the construction area have contributed a lot to the project’s delays and cost overruns. These geological complexities have necessitated more safety and security measures. This also adds to the overall expense.
Contractor Challenges
Working on the mountain and forest terrain needs a lot of skill and effort as these geographical regions may come up with the most unexpected challenges. Hence, in this case, finding the most skilled workforce has been a major contributing factor in delaying the process.
Recruiting contractors and assembling a capable workforce has been slow and challenging. A history of construction work stopping due to legal issues and difficulty in securing experienced crews have hampered the project’s progress.
Legal and Environmental Controversies
The project has faced legal and environmental controversies as well since its inception, with concerns raised about its impact on forests, waterways, and endangered species.
The project has been viewed by environmental organizations as an investment in fossil fuel infrastructure at a time when the emphasis is on transitioning to renewable energy to combat climate change. The legal authorities have put a series of charges on the project that has been stayed in the hearing of the Supreme Court. However, the verdict came in favour of the project to get it resumed.
Sum Up
The mega pipeline project in the Jefferson National Forest to cross the Mountain Valley has once again been delayed after a series of issues since its beginning. the unexpected delays in the project have raised the completion cost from $3.5 to $7.2 billion. The project will run from part of northern West Virginia and will end in the Central part of Virginia. Further, this project will connect to the Transco Pipeline making it the mega project of its kind.